Late 2020 KBS were appointed Electrical contractor for the new Sales floor AC installation at Waitrose & Partners Gloucester Road.

Working to a 5 week construction programme with Kershaw Mechanical Services as main contractor, KBS were to install a New 3 phase Distribution board that supplied four new Mitsubishi condensers, BMS Cabling & with our trusted Sub-contractor modifications to the existing BMS Panel.

Services Provider

  • Electrical Installation
  • Small Power
  • Main Switch Panels & Distribution System
  • BMS Systems
  • Fire Alarm
  • Containment Systems
  • Test & Commission