Services Provided
- Full Design
- Containment Systems
- Red FP200 Gold Cabling
- Test & Commission
- Small Power
THE OPPORTUNITY
In early 2021, KBS were appointed to carry out the full fire alarm upgrade to this well-established building that has served the John Lewis Partnership for many years. We were proud to be the main contractor for this project.
THE DELIVERY
Working to a 6-week programme, KBS and its trusted suppliers designed, installed and commissioned a new addressable Fire Alarm System. The team were required to complete the project with fire rated cable, metal containment, fastenings, interface units to shutdown plant and equipment and smoke & heat detection.
THE OUTCOME
The project was completed within the given time frame and budget for our client, leading to our successful appointment on several projects for John Lewis.
Unit 7 – 8 Forest Court
Oaklands Park, Wokingham RG41 2FD